During project execution, the project team realizes that the power outlet for imported equipment is not compatible with the current customer’s electrical infrastructure. This event was originally identified as a risk during earlier stages of the project and the associated risk response indicated a plan to purchase a new power adapter.

During project execution, the project team realizes that the power outlet for imported equipment is not compatible with the current customer’s electrical infrastructure. This event was originally identified as a risk during earlier stages of the project and the associated risk response indicated a plan to purchase a new power adapter.
Which project fund will be used to cover this cost?
A. Management reserve
B. Management budget
C. Project budget
D. Contingency reserve