When you fast track the project which of the following are likely to increase?

You work as a project manager for BlueWell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decided, with your stakeholders’ approval, to fast track the project work to get the project done faster. When you fast track the project which of the following are likely to increase?
A. Costs
B. Quality control concerns
C. Human resource needs
D. Risks