A risk facilitator is creating an outline for the risk management plan. To ensure alignment with the project’s objectives, and to develop and recommend the project’s risk strategy, what should be referenced to create this?

A risk facilitator is creating an outline for the risk management plan. To ensure alignment with the project’s objectives, and to develop and recommend the project’s risk strategy, what should be referenced to create this?
A. Project management plan, project charter, stakeholder register, and organizational process assets
B. Risk register, project charter, stakeholder register, and organizational process assets
C. Project management plan, risk register, stakeholder register, and organizational process assets
D. Strengths, weaknesses, opportunities, and threats (SWOT) analysis, project charter, stakeholder register, and organizational process assets

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.