You work as a project manager for SoftTech Inc. You have implemented the risk action plan and it was not effective. What type of plan should you as a project manager will create for implementation if a selected risk strategy fails to be fully effective?
A. Mitigation management plan
B. Mitigation plan
C. Fallback plan
D. Risk response plan