What is the project’s cost performance index?

You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete – though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project’s cost performance index?
A. 1.06
B. 0.92
C. -$30,647
D. 0.93