The project manager needs to create a risk management plan for a high risk project, but the company’s senior management does not see value in spending time documenting major risks instead of leading the project. What is the most appropriate action for the project manager to take first?

The project manager needs to create a risk management plan for a high risk project, but the company’s senior management does not see value in spending time documenting major risks instead of leading the project. What is the most appropriate action for the project manager to take first?
A. Develop a risk register and present it to the senior management
B. Hire a risk consultant to identity the major risks.
C. Develop a risk management plan and present it to the sponsor.
D. Document all identified risks.