How much capital should the project set aside for the risk contingency reserve?

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the project set aside for the risk contingency reserve?

A. $142,000
B. $41,750
C. $23,750
D. $232,000