Which output of the manage stakeholder expectations process can create risks?

Harold is the project manager of a large project in his organization. He has been actively communicating and working with the project stakeholders. One of the outputs of the manage stakeholder expectations process can actually create new risk events for Harold’s project. Which output of the manage stakeholder expectations process can create risks?
A. Project document updates
B. Change requests
C. Organizational process assets updates
D. Project management plan updates