Which one of the following will NOT help Wendy to perform this project management activity?

Wendy is about to perform qualitative risk analysis on the identified risks within her project. Which one of the following will NOT help Wendy to perform this project management activity?
A. Project scope statement
B. Risk management plan
C. Risk register
D. Stakeholder register

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply