Which one of the following is NOT a determination that is made by the risk monitoring and controlling process?

In addition to monitoring and controlling the project risks for their status and information the risk monitoring and controlling process accomplishes four key things for a project. Which one of the following is NOT a determination that is made by the risk monitoring and controlling process?
A. Determines if the project assumptions are still valid
B. Determines if the risk management policies and procedures are being followed
C. Determines if the risk contingency reserves should be modified to be in alignment with the current riskassessment
D. Determines if the project constraints are still valid