A number of items may be part of the schedule data for the project. The amount of additional detail will vary, but the data should include all the following items
EXCEPT______________
A. Schedule activities
B. Activity attributes
C. Identified assumptions
D. Resource breakdown structure
Correct Answer: D
Explanation/Reference:
Schedule data for the project schedule includes a number of items as it collects the information used to describe and control the schedule. It includes schedule milestones, schedule activities, activity attributes, and assumptions and constraints. It may include resource histograms, alternate schedules, contingency reserves cash-flow projections, and order and delivery schedules.
How To Pass PMP Exam?
PMI PMP PDF dumps.
High quality PMP pdf and software. VALID exam to help you pass.
|
|
Download Printable PDF. VALID exam to help you PASS.
|
|