The close project or phase process addresses actions and activities concerning all of the following EXCEPT______________.

The close project or phase process addresses actions and activities concerning all of the following EXCEPT______________.
A. Completion or exit criteria for the project or phase have been met
B. Stakeholder approval that the project has meet their requirements
C. Review of the project and/or phase information for potential future use
D. Documentation that completed deliverables have been accepted