What should the project manager have developed to prevent this?

While managing a project for a multinational company, a project manager continues to accept changes from the client to maintain a good relationship and secure new business. Three quarters of the way through the project, the budget is depleted.
What should the project manager have developed to prevent this?
A. Project scope statement
B. Cost management plan
C. Statement of work (SOW)
D. Change management plan