The other team members also work in the human resources department. The project charter should be issued by______________.

You are a personnel management specialist recently assigned to a project team working on a team-based reward and recognition system. The other team members also work in the human resources department. The project charter should be issued by______________.
A. The project manager
B. The client
C. A sponsor
D. A member of the PMO who has jurisdiction over human resources