What can be concluded about the activity?

An activity has an early start date of the 10th and a late start date of the 19th. The activity has a duration of four days. There are no non workdays. From the information given, what can be concluded about the activity?
A. Total float for the activity is nine days.
B. The early finish date of the activity is the end of the day on the 14th.
C. The late finish date is the 25th.
D. The activity can be completed in two days if the resources devoted to it are doubled.