What should the project team do next?

At the first team meeting, the project manager uses the risks noted in the project charter as a starting point for developing the risk register. After identifying the risks, what should the project team do next?
A. Calculate the management reserve.
B. Develop contingent response strategies.
C. Populate a probability and impact matrix.
D. Perform quantitative risk analysis.