What should the project manager do?

A company is running two projects with different priorities and timelines. The project charter for project A has been approved, and the project is on schedule. One of the stakeholders requests that project B’s requirements be included in project A.
What should the project manager do?
A. Submit a change request to the change control board (CCB).
B. Obtain management approval.
C. Perform an impact analysis on the scope and schedule.
D. Update the project management plan.