When appropriate configuration information should be provided and regarding the status of proposed and approved changes effectively is done through______________

Recording and reporting information regarding when appropriate configuration information should be provided and regarding the status of proposed and approved changes effectively is done through______________
A. Configuration status accounting
B. Configuration verification and audit
C. Project management methodology
D. A project management information system (PMIS)