Which of the following is a technique the project manager should use with the team to focus on the right areas to make changes that could improve the quality of the data-capture process?

A university has a project to implement a new online application system for new entrants. The pilot solution shows that a significant number of applications have captured incomplete and inaccurate data. The project team, subject matter exeperts (SMEs), and key stakeholders held a workshop to investigate the causes of these errors.
Which of the following is a technique the project manager should use with the team to focus on the right areas to make changes that could improve the quality of the data-capture process?
A. Cause-and-effect diagram
B. Affinity diagram
C. Influence diagram
D. Fishbone diagram

How To Pass PMP Exam?

PMI PMP PDF dumps.

High quality PMP pdf and software. VALID exam to help you pass.

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.