Change is inevitable on projects. Uncontrolled changes are often referred to as______________
A. Rework
B. Scope creep
C. Configuration items
D. Emergency changes
Correct Answer: B
Explanation/Reference:
Project scope creep is typically the result of uncontrolled changes. Scope control works to control the impact of any project scope changes.