Which risk analysis diagram is used to compare the relative importance and impact of variables that have a high degree of uncertainty to those that are more stable?

Which risk analysis diagram is used to compare the relative importance and impact of variables that have a high degree of uncertainty to those that are more stable?
A. Decision tree
B. Tomado
C. Ishikawa
D. Monte Carlo