Home » PMI » PMP v.2 » Stakeholder engagement must be controlled on a continuous basis for it to be effective. You realize a number of project documents can be useful for you as a project manager. An example is______________
Stakeholder engagement must be controlled on a continuous basis for it to be effective. You realize a number of project documents can be useful for you as a project manager. An example is______________
A. Technical performance measures
B. Change log
C. Actual costs
D. Start and finish dates of schedule activities
Correct Answer: B
Explanation/Reference:
Projects involve change, and most everyone tends to resist it. A change log is useful to review in the control stakeholder engagement process. Other useful documents are the schedule, stakeholder register, issue log, and project communications.
How To Pass PMP Exam?
PMI PMP PDF dumps.
High quality PMP pdf and software. VALID exam to help you pass.
|
|
Download Printable PDF. VALID exam to help you PASS.
|
|