What should the project manager have done to avoid this issue?

The building of an industrial plant has been stopped for four months due to region-specific prohibitions. What should the project manager have done to avoid this issue?
A. Made a prioritized list of the project constraints
B. Crashed the project schedule
C. Identified this as a risk in the risk log
D. Documented all assumptions