What should the project manager do next?

During the budget approval process, a project manager makes some initial estimations that include scope and potential risk reserves. After submitting the budget for approval, the project manager is asked to submit one that is more accurate.
What should the project manager do next?
A. Run a bottom-up estimation and provide a new budget.
B. Perform a cost-benefit analysis to support the current budget estimations.
C. Conduct a top-down estimation and provide a new budget.
D. Review the justification of the estimates to ensure that they are accurate and current.