What should the project manager do to resolve this?

Upon completion of the deliverables, the customer finds that they fail to meet the required functionality specifications. What should the project manager do to resolve this?
A. Update the project documentation.
B. Review the requirements management plan.
C. Consult the quality management plan.
D. Identify the process controls