Home » PMI » PMP v.2 » As project manager, you need a relatively fast and informal method addressing disagreements with contractors. One such method is to submit the issue in question-to an impartial third party for resolution. This process is known as______________
As project manager, you need a relatively fast and informal method addressing disagreements with contractors. One such method is to submit the issue in question-to an impartial third party for resolution. This process is known as______________
A. Alternative dispute resolution
B. Problem processing
C. Steering resolution
D. Mediation litigation
Correct Answer: A
Explanation/Reference:
Alternative dispute resolution, or dispute resolution, is a relatively informal way to address differences of opinion on contracts. Its purpose is to address such issues without having to seek formal legal redress through the courts.