Home » PMI » PMP v.2 » You are developing radio frequency (RF) technology that will improve overnight package delivery. You ask each stakeholder to estimate the most optimistic package delivery time using the RF technology, the most pessimistic time, and the most likely time. This shows that for your next step you plan to______________
You are developing radio frequency (RF) technology that will improve overnight package delivery. You ask each stakeholder to estimate the most optimistic package delivery time using the RF technology, the most pessimistic time, and the most likely time. This shows that for your next step you plan to______________
A. Use a beta or triangular probability distribution
B. Conduct a sensitivity analysis
C. Structure a decision analysis as a decision tree
D. Determine the strategy for risk response
Correct Answer: A
Explanation/Reference:
Interviews often are used to help quantify the probability and consequences of risks on project objectives. The type of information collected during the interview depends on the type of probability distribution that is used. A beta or triangular distribution is used widely when information is gathered on the optimistic (low), pessimistic (high), and most likely scenarios.
How To Pass PMP Exam?
PMI PMP PDF dumps.
High quality PMP pdf and software. VALID exam to help you pass.
|
|
Download Printable PDF. VALID exam to help you PASS.
|
|