A project health check identified a risk that your project would not be completed on time. As a result, you are quantifying the project’s risk exposure and determining what cost and schedule contingency reserves might be needed. You performed a schedule risk analysis using Monte Carlo analysis. The basis for your schedule risk analysis is the______________
A. WBS
B. Gantt chart
C. Schedule network diagram and duration estimates
D. Probability/impact risk rating matrix
Correct Answer: C
Explanation/Reference:
When determining the likelihood of meeting the project’s schedule end date through Monte Carlo, the schedule network diagram and duration estimate are used as inputs to the simulation program. Cost risk, on the other hand, uses cost estimates from the WBS.
How To Pass PMP Exam?
PMI PMP PDF dumps.
High quality PMP pdf and software. VALID exam to help you pass.
|
|
Download Printable PDF. VALID exam to help you PASS.
|
|