What cost and schedule contingency reserves might be needed. You performed a schedule risk analysis using Monte Carlo analysis. The basis for your schedule risk analysis is the______________

A project health check identified a risk that your project would not be completed on time. As a result, you are quantifying the project’s risk exposure and determining what cost and schedule contingency reserves might be needed. You performed a schedule risk analysis using Monte Carlo analysis. The basis for your schedule risk analysis is the______________
A. WBS
B. Gantt chart
C. Schedule network diagram and duration estimates
D. Probability/impact risk rating matrix