Home » PMI » PMP v.2 » The project manager has requested all expert team members to complete an anonymous questionnaire to identify possible risks. This is an example of a technique known as the:
The project manager has requested all expert team members to complete an anonymous questionnaire to identify possible risks. This is an example of a technique known as the:
A. interview technique
B. information gathering technique
C. Delphi technique
D. feedback technique
Correct Answer: C
Explanation/Reference: