Recognizing operations management is different than project management, as the project manager for a new line of electrical tractors to avoid the need to use costly fuel, you realize a best practice is to______________

Recognizing operations management is different than project management, as the project manager for a new line of electrical tractors to avoid the need to use costly fuel, you realize a best practice is to______________
A. Document the operational managers’ influence either positive or negative in the stakeholder register
B. Offer to include the operational managers in all project phases
C. Recognize that the operational managers are only involved once they have ongoing responsibility for the product, service, or result
D. Realize the operations managers have key responsibilities on the Portfolio Review Board

How To Pass PMP Exam?

PMI PMP PDF dumps.

High quality PMP pdf and software. VALID exam to help you pass.

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.