During a project’s initiation, project manager A realizes that the project id dependent on and linked to other projects. Project manager A attempts to change the plans of these other projects. The other project managers feel that project manager A has overstepped boundaries.
Which document does project manager A need to revisit?
A. Scope management plan
B. Statement of work (SOW)
C. Organizational process assets
D. Project charter