What should the project manager have done to avoid this?

To address security vulnerability during a project blackout period, a project manager must obtain approval to deploy an environment configuration change. The release management team rejects the change request due to lack of supporting information.
What should the project manager have done to avoid this?
A. Obtained information from external communities to support the risk
B. Asked security experts to assist with obtaining approval
C. Documented the consequences of failing to make the change
D. Logged it as a high-probability and high-impact risk in the risk register