Which could push the go-live date. This delay may result in the regulatory requirement becoming mandatory for project implementation. What should the project manager do first?

A project has an external dependency on a changing regulatory requirement planned to go into effect after the project’s scheduled go-live date. The project team informs the project manager that a missed milestone caused a delay, which could push the go-live date. This delay may result in the regulatory requirement becoming mandatory for project implementation. What should the project manager do first?
A. Add more resources to ensure that the project is delivered before the regulatory requirement is in effect.
B. Revise the project scope to include the new regulatory requirement.
C. Update the risk register and risk ranking to reflect the impact of the delay
D. Review the consequences of noncompliance with the new regulatory requirement.

How To Pass PMP Exam?

PMI PMP PDF dumps.

High quality PMP pdf and software. VALID exam to help you pass.

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.