How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?
A. Keep satisfied
B. Keep informed
C. Manage closely
D. Monitor