What process is the project manager implementing?

During a project to create an organizational business plan, the project manager facilitates a strengths, weaknesses, opportunities, and threats (SWOT) analysis workshop with senior management. What process is the project manager implementing?
A. Plan Risk Management
B. Identify Risks
C. Perform Qualitative Risk Analysis
D. Plan Risk Responses