You are the project manager on a project to improve traffic flow in the company’s parking garage. You decide to use flowcharting to______________
A. Help anticipate how problems occur
B. Show dependencies between tasks
C. Show the results of a process
D. Forecast future outcomes
Correct Answer: A
Explanation/Reference:
Flowcharts depict the interrelationship of a system’s components and show the relationships among process steps. They are often referred to as process maps as they display the sequence of steps and the branching possibilities for a process that transforms one or more inputs into one or more outputs. Flowcharts show activities, decision points, branching loops, parallel paths, and the order of processing. As such, they aid the team in anticipating where quality problems might occur, which helps in developing approaches for dealing with these potential problems.
How To Pass PMP Exam?
PMI PMP PDF dumps.
High quality PMP pdf and software. VALID exam to help you pass.
|
|
Download Printable PDF. VALID exam to help you PASS.
|
|