Work performance information includes all the following EXCEPT______________
A. Started deliverables
B. Costs authorized and incurred
C. Progress of deliverables
D. Completed deliverables
Correct Answer: B
Explanation/Reference:
Work performance information is an output of validate scope. It emphasizes deliverables whether or not they have started, their progress, and ones that have finished or have been accepted.