Midway through a project’s execution phase, the client asks to add new product features. What should the project manager do first?
A. Review the project scope with project team members and the client.
B. Obtain scope-change approval from the change control board (CCB).
C. Reject the request.
D. Assess the impact of the request on the overall project management plan.