A project manager must track schedule variances over time. What tool or technique should be used to determine whether or not the variances are within acceptable limits?
A. Cause-and-effect diagram
B. Control chart
C. Scatter diagram
D. Control panel diagram
Correct Answer: B
Explanation/Reference: