During project planning, the project manager wants to transfer as many cost overrun risks as possible to the supplier. What type of contract should the project manager use?
A. Cost plus incentive fee (CPIF)
B. Cost plus fixed fee (CPFF)
C. Firm fixed price (FFP)
D. Fixed price with economic price adjustment (FPEPA)