A project manager has two projects of equal, strategic organizational importance. However, due to budget constraints, only one can be chosen. There are uncertainties and risks associated with both projects.
What tool or technique should the project manager use to decide which project to choose?
A. Simulations
B. Decision tree analysis
C. Sensitivity analysis
D. Influence diagrams