What is the estimate at completion (EAC) for this project and what does it represent?

According to the information in the grid, what is the estimate at completion (EAC) for this project and what does it represent?

A. US$9,000 – the original project budget
B. US$13,500 – the revised estimate for total project cost (based on performance to date)
C. US$13,500 – the original project budget
D. US$9,000 – the revised estimate for total project cost (based on performance to date)