A project manager notices that the project is behind schedule because materials delivery was delayed. The procurement team informs the project manager that
new government-imposed rules for the procurement of these materials caused this delay.
In what plan should these new rules be documented?
A. Procurement management
B. Communications management
C. Stakeholder engagement
D. Project management