How is the Acme project doing?

As of the fourth month on the Acme project, cumulative planned expenditures were $100,000.
Actual expenditures totaled $120,000. How is the Acme project doing?
A. It is ahead of schedule.
B. It is in trouble because of a cost overrun.
C. It will finish within the original budget.
D. The information is insufficient to make an assessment.