What is the project manager trying to avoid by doing this?

A customer demands several project scope updates, but the implementation team is working on task execution based on the project management plan. The project manager uses negotiation skills to obtain formal approval of these demands and have them communicated.
What is the project manager trying to avoid by doing this?
A. Project changes
B. Product rework
C. Scope creep
D. Budget overrun