Closing a project phase should not be delayed until project completion because______________.
A. Useful information may be lost
B. The project manager may be reassigned
C. Project team members may be reassigned by that time
D. Sellers are anxious for payments
Correct Answer: A
Explanation/Reference:
Closure includes collecting project records, ensuring that the records accurately reflect final specifications, analyzing project or phase success and effectiveness, and archiving such information for future use. Each phase of the project should be properly closed while important project information is still available.