Which of the following information is determined?

Performance review meetings are held to assess schedule activity and work packages over-running or under-running the budget and to determine any estimated funds needed to complete work in progress. Typically, if EV is being used, all but which of the following information is determined?
A. Variance analysis
B. Trend analysis
C. Time reporting systems
D. Earned value performance