Home » PMI » PMP v.2 » Which of the following information is determined?
Performance review meetings are held to assess schedule activity and work packages over-running or under-running the budget and to determine any estimated funds needed to complete work in progress. Typically, if EV is being used, all but which of the following information is determined?
A. Variance analysis
B. Trend analysis
C. Time reporting systems
D. Earned value performance
Correct Answer: C
Explanation/Reference:
Variance analysis focuses on cost and schedule to help explain the cause, issue, and corrective action. Trend analysis examines project performance over time to determine performance status. Earned value performance compares the performance measurement baseline to actual schedule and cost performance.
How To Pass PMP Exam?
PMI PMP PDF dumps.
High quality PMP pdf and software. VALID exam to help you pass.
|
|
Download Printable PDF. VALID exam to help you PASS.
|
|