An influential functional leader has removed a key team resource from a project. The activities on the critical path will be negatively affected by this action.
What should the project manager do?
A. Negotiate with and influence the functional leader to reverse their decision.
B. Engage the sponsor to discuss the importance of the resource with the functional leader.
C. Analyze the impact to the project management plan and submit a change request.
D. Acquire a replacement resource by following the resource management plan.