Detailed design has begun on a firm fixed price (FFP) contract, and the statement of work (SOW) has been clearly defined for the consultants. Now, an expert communicates to the consultants that additional work is needed.
How should the project manager proceed?
A. Approve the additional work.
B. Amend the FFP control to include the additional work.
C. Review the scope of the additional work.
D. Log the additional work in the risk register.