Which of the following formulas?

Consider the data in the table below.

Assume that your project consists only of these three activities. Your estimate at completion is $4,400.00. This means you are calculating your EAC by using which of the following formulas?
A. EAC = AC/EV × BAC
B. EAC = AC/EV × [work completed and in progress] + [actual (or revised) cost of work packages that have not started]
C. EAC = [Actual to date] + [all remaining work to be done at the planned cost including remaining work in progress]